1. 、结合行为教育开展好学生行为专项教育活动。
1. Combine behavior education to carry out special student behavior promotional activities.
2. 交接时工器具、拖布不全或多或少摆放混乱扣 1分。(罚班组长)备注:接班时,少或多且摆放混乱没有及时上报,扣罚当班班组长。
2. If tools, brooms, and cleaning equipment are not complete or are placed in a disorganized manner during the handover, 1 point will be deducted. (Punish the team leader.) Note: If there is a shortage or excess, and the placement is disorganized at the time of taking over, and this is not reported in a timely manner, the team leader on duty will be penalized.
3. 车间联查时发现的违规操作项和野蛮操作出现一次扣2分 (操作人员、班组长、工段长按规定进行罚款)
3. For each violation of operation standards and rough handling discovered during the joint inspection of workshops, two points will be deducted once (operators, team leaders, and workshop leaders will be fined according to the regulations).
4. 项目质量部积极推进质量样板工程创建活动。按照《中国寰球工程公司20xx年度质量样板工程创建活动方案》(中寰质安函〔20xx〕56号)要求,对照考核标准,组织开展自检自查活动,组织对申报质量样板工程不定期开展自评活动,确保申报项目达到质量样板工程要求。争创国家、行业、地方(省、市、自治区)的质量奖和优质工程,积极引进先进的质量管理方法,总结质量管理先进经验,提高质量管理水平,积极参加质量标杆评选活动,不断提升寰球公司EPC工程项目的质量水平。
4. The Project Quality Department actively promotes the creation of quality model projects. In accordance with the "China Global Engineering Company's 20xx Quality Model Project Creation Activity Plan" (CGEC-QAS Letter [20xx] 56), against the assessment criteria, it organizes self-inspection and self-audit activities, and organizes irregular self-evaluation activities for the quality model projects申报. This ensures that the申报 projects meet the requirements of quality model projects. It strives to win national, industry, and local (provincial, municipal, autonomous regions) quality awards and excellent engineering projects, actively introduces advanced quality management methods, summarizes advanced quality management experiences, improves the level of quality management, actively participates in the quality benchmark selection activities, and continuously enhances the quality level of the EPC engineering projects of the China Global Group.
5. 为了有效的实现过程质量控制,项目部实行了目标管理,一级抓一级,层层抓落实,质量验收严格执行“三检”制度、隐蔽工程验收及工序交接制度、检试验认可制度。分项工程开工前对施工人员交底,完成进场材料检测及施工机具验收;施工过程中,技术人员跟班作业,及时指导施工和监督工程质量,严格工序报验制度的落实。
5. In order to effectively implement process quality control, the project department has implemented target management, with a top-down approach, ensuring that each level is responsible for its own execution. The quality acceptance strictly follows the "three inspections" system, hidden work acceptance and process handover system, and inspection and test approval system. Before the start of the sub-project, the construction personnel are briefed, and the incoming material inspection and construction equipment acceptance are completed; during the construction process, technical personnel work on-site, providing timely guidance for construction and supervising the quality of construction work, and strictly implementing the process reporting and acceptance system.
6. 六是开展执法打假专项活动。由局稽查队牵头,以关系人民群众身体健康和生命财产安全为打假重点,对农资、建材等产品集中开展打假专项行动,从源头严厉打击假冒伪劣违法活动。七是极积配合相关部门开展“质量诚信承诺”活动。(局稽查队牵头,相关股室配合)
6. The sixth measure is to launch a special campaign for law enforcement and anti-counterfeiting. Led by the Bureau's Inspection and Audit Team, with the focus on protecting people's health and safety of property, special anti-counterfeiting operations are conducted on agricultural inputs, building materials and other products, aiming to severely crack down on illegal activities of counterfeit and shoddy products from the source. The seventh measure is to actively cooperate with relevant departments to carry out the "Quality Integrity Pledge" activity. (Led by the Bureau's Inspection and Audit Team, with support from relevant sections.)
7. 为了更好开展质量月活动,机加工司召开全厂员工会议进行活动动员,456开展质量月活动的目的和要求进行了简单的叙述,并宣布质量月活动开始。456对质量月活动的具体实施,活动安排等问题做了简明扼要的评述。564各车间的改善情况做了具体的要求,质量月活动正式拉开序幕。要求要以质量月活动为契机,营造“人人关心质量、人人重视质量”的氛围。
7. In order to better carry out the Quality Month activities, the Machining Department held a meeting with all the employees for mobilization. A brief description of the objectives and requirements of the Quality Month activities was given, and the start of the Quality Month activities was announced. A concise review of the specific implementation and activity arrangements for the Quality Month activities was provided. Specific requirements were made for the improvement of each workshop, marking the official opening of the Quality Month activities. It is required to take the Quality Month activities as an opportunity to create an atmosphere where "everybody cares about quality and everybody values quality."
8. 为有效实施全员重质量,共筑强企梦,增强员工质量意识,提升质量管理水平,提高产品、工程和服务质量,根据集团公司《关于开展
8. In order to effectively implement the all-employee focus on quality, work together to build a strong enterprise dream, enhance employees' quality awareness, improve the level of quality management, and elevate the quality of products, projects, and services, according to the Group Corporation's "Notice on Carrying Out..."
9. 加强领导,认真组织,精心安排。项目各部门、承包商各项目部要围绕今年“质量月”活动主题,结合实际,制订出具体的活动计划,切实把20xx年“质量月”活动落到实处。
9. Strengthen leadership, organize seriously, and make careful arrangements. The departments of the project and the project departments of the contractors should focus on the theme of this year's "Quality Month" activities, combine them with the actual situation, formulate specific activity plans, and effectively implement the "Quality Month" activities in 20xx.
10. 为了提高公司产品质量,提高员工的工作质量和进取性,提高部门人员职责心,增强企业凝聚力,20XX年9月我公司开展了以“全员行动,提高质量”为主题的“质量月”活动,在公司的领导下,各车间高度重视、精心组织、严格要求,各车间的质量水平取得了显著的成效,产品合格率较前期有了大幅度的提升。现将活动有关情景总结如下:
10. In order to enhance the quality of our company's products, improve the work quality and proactiveness of our employees, strengthen the sense of responsibility among department staff, and enhance corporate cohesion, in September of 20XX, our company launched a "Quality Month" activity themed "All-for-One Action, Improve Quality." Under the leadership of the company, each workshop attached great importance, organized meticulously, and imposed strict requirements. As a result, the quality levels of all workshops achieved remarkable results, and the pass rate of products saw a significant increase compared to the previous period. The following is a summary of the key situations related to the activity:
11. 产品质量源自员工的精心操作;精心操作体现员工的职业道德。
11. Product quality originates from the careful operation of employees; careful operation reflects the professional ethics of the employees.
12. 本次活动以进一步贯彻落实“精益求精、精诚服务;引领技术潮流,追求完美品质”的质量方针为主线,通过开展多种形式的教育、培训和产品实现过程中的质量控制活动,全员参与,全面提高员工素质,强化质量意识,视质量为生命;进一步加强质量管理控制工作,确保本公司的质量管理体系有效运行,为客户提供更优质的产品。
12. This event takes the quality policy of "Continuous Improvement, Dedicated Service; Leading Technological Trends, Pursuing Perfect Quality" as the main thread, through the implementation of various forms of education, training, and quality control activities during the product realization process, with the participation of all staff, aiming to comprehensively improve the quality of employees, strengthen the awareness of quality, and regard quality as life. Furthermore, it aims to enhance the quality management and control work to ensure the effective operation of the company's quality management system and provide customers with superior products.
13. 按照公司20xx年总体工作部署和公司秋检工作方案部署,组织落实xx场各项安全组织技术措施方案,开展xx场季节性反事故措施实施工作,保障生产工作的正常进行,消除设备缺陷隐患。
13. In accordance with the company's overall work plan for the year 20xx and the deployment of the autumn inspection work plan, organize and implement the safety organization and technical measures for various safety projects at xx site, carry out seasonal accident prevention measures at xx site, ensure the normal progress of production work, and eliminate potential hazards of equipment defects.
14. 进入“质量月”,电慈阀事业部针对新进人员对质量知识不熟悉、对质量工作认识不深刻的现象,由质量处处长王丽红组织进行了质量知识培训,培训内容除了学习Q型质量知识外,还结合实际,就生产过程中应注意的事项,如严格按照工艺要求加工;生产过程的三不原则-----对不合格品不接受、不生产、不放过;生产过程如何做好零件的防护;如何做好工量器具、设备的维护保养;生产过程中的环境保持等等,并给大家 强调 ,质量工作的基础是预防,要第一次就把事情做好;质量工作的重点是持续改进,对加工中的新方法、新建议,要大胆提出,同时,学习了以往生产过程中发生的一些案例,从以往发生的质量问题中总结经验,吸取教训。
14. Entering the "Quality Month," the Electric Mercy Valve Department, in response to the new staff's unfamiliarity with quality knowledge and their shallow understanding of quality work, organized a quality knowledge training session led by the Quality Department Director, Ms. Wang Lihong. The training content included not only the study of Q-type quality knowledge but also, in conjunction with actual practices, addressed matters to be noted during the production process, such as strictly following the process requirements for processing; the three non-principles of the production process - not accepting, not producing, and not passing by substandard products; how to protect components in the production process; how to maintain and keep tools and equipment in good condition; environmental maintenance during the production process, etc. Ms. Wang Lihong emphasized that the foundation of quality work is prevention, and things should be done right the first time. The focus of quality work is continuous improvement, so new methods and suggestions during the processing should be boldly proposed. Additionally, some past cases from the production process were studied, and experiences were summed up and lessons learned from the quality issues that had occurred in the past.
15. 设备的运行状况,决定着公司长远发展的生产效益。公司风电场重点对设备定检消缺和设备档案归档整理工作进行了分工布置,要求各专业、各岗位按照设备管理要求,正规建档建册,合理定级评级,全方位梳理、跟踪。我们严格要求各运行值一天两次设备巡检,各专业专工一周一次设备、系统运行状况检查,发现问题及时汇报并督促处理,要求xx厂家质保人员随时对xx故障停机进行消缺处理,保证主、辅设备正确投入率100%。其次,我们还在检修中严把检修工艺关,明确验收质量标准,要求设备专责人必须深入生产现场了解设备状况,检查设备检修质量,及时整理保存设备运行验收资料。
15. The operating condition of the equipment determines the production efficiency for the company's long-term development. The company's wind farm has focused on dividing and deploying the work of equipment regular inspections and defect elimination, as well as equipment file organization. It requires each professional team and position to establish formal files and records in accordance with equipment management requirements, reasonably classify and rate, and comprehensively sort out and track. We strictly require the operation shifts to conduct two rounds of equipment inspections a day, each professional specialist to carry out a weekly inspection of equipment and system operating conditions, promptly report any issues and督促处理, and require the quality assurance personnel from the xx manufacturer to carry out defect elimination for any xx malfunctioning stoppages at any time, ensuring a correct and efficient operation rate of 100% for both main and auxiliary equipment. Furthermore, during maintenance, we strictly control the maintenance process, clearly define quality standards for acceptance, and require the responsible person for equipment to deeply understand the equipment conditions at the production site, inspect the quality of equipment maintenance, and promptly organize and preserve the operating acceptance documents of the equipment.
16. 现场卫生、工艺卫生方面各占20分:(由车间主管。品控员。督查员。质检员等)进行检查(
16. Sanitation and hygiene on-site, and process hygiene each account for 20 points: (Inspected by workshop supervisor, quality control staff, inspector, quality inspector, etc.)
17. 进取地与中华建筑报社人才培训中心合作,为项目部的高级施工管理人才进行新颁布的法规文件、规范标准以及新技术、新材料的运用等方面的培训。并成立了中国水电九局思林电站农民工技能培训分校,对分包协作的40余人进行每周一次的培训。切实从理论上提高了项目部质量管理人员的管理水平,也极大地提高了一线施工人员的施工技能。
17. Actively cooperate with the Talent Training Center of China Construction Press to provide training for senior construction management personnel in the project department on the newly promulgated regulations, standards, as well as the application of new technologies and materials. In addition, the branch school of the China水电 Ninth Bureau's Siming Hydropower Plant农民工 skill training was established, conducting weekly training for over 40 subcontracted and collaborative personnel. This has effectively improved the management level of quality management personnel in the project department from a theoretical perspective, and also greatly enhanced the construction skills of front-line construction personnel.
18. 9月31日本次质量月活动经过全体人员共同努力圆满结束,,经过本次质理月活动大大提高了质量意识,提高了人员的技能水平和管理水平,到达了预期的目标,并取得了良好的社会效益。质量月使我公司的质量有了很大的提高,期望各车间坚持目前的良好形势,对质量常抓不懈,构成月月是质量月,日日抓质量的良好氛围,使我公司的质量不断的上新台阶,树立我公司的质量信誉,创立品牌,在市场中立于不败之地。
18. The quality month activity, which concluded on September 31st, was successfully completed through the joint efforts of all staff. The activity significantly enhanced the quality awareness, improved the skills and management levels of the personnel, achieved the expected goals, and yielded positive social benefits. The quality month has greatly improved the quality of our company. We hope that all workshops will maintain the current favorable situation, consistently focus on quality, and create a good atmosphere where every month is a quality month and every day is dedicated to quality. This will enable our company's quality to continuously reach new heights, establish our company's quality credibility, create a brand, and maintain a competitive edge in the market.
19. 严格控制生产过程质量为了有效的实现过程质量控制,各车间员工提高自检能力,生产过程中加强了自检。车间检验人员提高了检验的力度和频率,所有尺寸按照公司内控标准严格执行,并详细做好记录。各车间主任严格管理各车间的质量,使产品质量都有了明显的提高。
19. Strict control of the production process quality In order to effectively implement process quality control, the employees in each workshop have improved their self-inspection capabilities and strengthened self-inspection during the production process. The inspection personnel in the workshops have increased the intensity and frequency of inspections, and all dimensions are strictly implemented in accordance with the company's internal control standards, with detailed records being kept. The workshop directors have strictly managed the quality in their respective workshops, resulting in a significant improvement in product quality.
20. 放学在校门、和学校西侧胡同内和东升楼小区内聚集的行为。
20. Behaviors of gathering at the school gate, in the alley to the west of the school, and within the Dongshenglou residential area after school.
21. 为增强全员质量意识,深入贯彻“公司质量月”的思想,10月16日上午,新华公司组织各部门和车间生产人员到xx卷烟厂进行参观学习。
21. In order to enhance the quality awareness of all staff and deeply implement the spirit of "Company Quality Month", on the morning of October 16th, Xin Hua Company organized personnel from all departments and workshops to visit and learn at XX Cigarette Factory.
22. 为了更好开展质量月活动,20XX年8月31日午时公司召开全公司员工会议进行活动动员,邵总对开展质量月活动的目的和要求进行了简单的叙述,并宣布质量月活动开始。李总对质量月活动的具体实施,活动安排等问题做了简明扼要的评述,对各车间的改善情景做了具体的要求,质量月活动正式拉开序幕。要求要以质量月活动为契机,营造“人人关心质量、人人重视质量”的氛围。
22. In order to better carry out the Quality Month activities, a company-wide staff meeting was held at noon on August 31, 20XX to mobilize for the event. President Shao gave a brief introduction to the purpose and requirements of the Quality Month activities and announced the start of the campaign. President Li made a concise review of the specific implementation and arrangements for the Quality Month activities, made specific requirements for the improvement situations in each workshop, and officially launched the Quality Month campaign. It is required that the opportunity be taken to create an atmosphere where "every person cares about quality and every person values quality."
23. 组织开展降低建筑工程质量通病研究和预防工作
23. Organize and carry out research and prevention work on reducing common quality problems in construction projects.
24. 活动时间 :
24. Activity Time:
25. 通过此次活动的开展,各工段的渺小环节得到了有效的节制。前段工序中板件的轻拿轻放,机械的勤修勤检,工艺的过细指点,孔位、槽位尺寸的偏差得到了有效的掌握;中段工序面油、底油的操作及技巧得到了较大的改良提高;后段包装部通过培训,冲破重点、难点,抓尾货,少包、错包等景象得到有效的遏制;来料处针对板件的划伤等质量问题提出和制定了切实可行的方案,同时派员驻厂跟踪,大大的降低了因为来料原因此下降生产效率的比率,实现了生产与打算同步的喜人局面。
25. Through the implementation of this activity, the minor links in each workshop have been effectively controlled. The gentle handling of sheet metal parts in the early stage, the frequent maintenance and inspection of machinery, and the detailed guidance on technology have effectively mastered the deviations in hole and slot dimensions; the operation and skills of surface oil and bottom oil in the middle stage have been significantly improved; in the later packaging section, through training, the key and difficult points have been broken through, and the phenomena of insufficient packaging, incorrect packaging, etc. have been effectively curbed; the incoming material department proposed and formulated practical and feasible solutions for quality issues such as scratches on sheet metal parts, and at the same time, sent personnel to the factory for follow-up, greatly reducing the rate of production efficiency decline due to incoming material reasons, and achieving a pleasing situation where production and planning are in sync.
26. 在实施阶段,各单位结合集团公司质量提升要求,围绕公司及本单位的质量工作目标和重点任务,扎实开展质量对标提升活动。认真组织开展质量法规和制度执行情况的专项督查、质量隐患排查整治、质量工艺纪律整顿等活动,全面排查质量隐患和风险。加强质量培训,针对各层次员工的不同需求,分类、分级开展质量教育培训活动。
26. In the implementation phase, various units combine the quality improvement requirements of the group company, focusing on the quality work objectives and key tasks of the company and the unit, to solidly carry out quality benchmarking and improvement activities. Carefully organize special inspections of the implementation of quality regulations and systems, quality隐患排查整治, and quality discipline rectification, etc., to comprehensively investigate and eliminate quality hazards and risks. Strengthen quality training, and in accordance with the different needs of employees at various levels, categorize and grade quality education and training activities.
27. (以下员工不合格项按车间管理规定进行惩罚,由班组长开据罚款单;班组长不合格项,由工段长开据罚款单,工段长的不合格项由生产办开据罚款单)
27. (The不合格items of the following staff will be penalized according to the workshop regulations, with the team leader issuing the penalty notice; if the team leader has不合格items, the penalty notice will be issued by the foreman, and if the foreman has不合格items, the penalty notice will be issued by the production office.)
28. 、9月16日—9月20日寰球现场项目部组织对施工现场进行第二次施工现场的质量大检查(三查四定或中交前大检查),评出优秀承包商,
28. From September 16th to September 20th, the Global On-site Project Department organized the second quality inspection of the construction site (the "Three Inspections and Four Determinations" or the pre-handover major inspection), and evaluated outstanding contractors.
29. 为树立质量意识,提高产品质量,x焦煤集团公司决定在9月1日至9月30日开展以“提质量,创品牌,增效益,共筑全球炼焦煤供给强企之基”为主题的“质量月”活动,并对活动内容及要求进行了详细安排部署。
29. In order to establish a quality awareness and improve product quality, the X Jiaomei Group Co., Ltd. has decided to launch a "Quality Month" activity from September 1st to September 30th, themed "Enhance quality, create brands, increase benefits, and jointly build a strong enterprise in global coking coal supply." Detailed arrangements have been made for the content and requirements of the activity.
30. 为了确保活动有序地进行,我们需要提前开始活动方案制定工作,活动方案是阐明活动时间,地点,目的,预期效果,预算及活动方法等的书面计划。我们该怎么去写活动方案呢?
30. In order to ensure the orderly progress of the event, we need to start the planning work for the event plan early. The event plan is a written document that clarifies the event's time, location, purpose, expected outcomes, budget, and methods of the event. How should we write the event plan?
31. 与行为专项相结合,在学生中广泛开展“爱我五中、爱我班级”活动,鼓励学生爱护环境、爱护公物。
31. In conjunction with the behavior special project, widely carry out the activity "Love Our No.5 High School, Love Our Class" among students, and encourage them to cherish the environment and public property.
32. 、以质量月和专项治理为依托,搞好四个活动:
32. Based on the Quality Month and special rectification efforts, carry out four activities:
33. 矿车修造厂组织员工进行了座谈,他们从不一样的角度畅谈了产品质量的重要性,表示只有产品质量上去了才能打造品牌,才能得到客户的认可。在生产管理中,车间管理人员及操作者是关键,只有他们认识到企业的长远发展离不开产品质量,才能真正的生产出创品牌的产品。
33. The mine car repair and manufacturing factory organized a discussion among its employees, where they freely discussed the importance of product quality from different perspectives. They expressed that only when product quality improves can a brand be established and recognized by customers. In production management, the workshop managers and operators are the key. Only when they realize that the long-term development of the enterprise is inseparable from product quality can they truly produce products that create a brand.
34. 对全车间员工进行了量具使用的培训。结构车间:坚持定期会议,提高员工的质量意识,每天生产结束后,质检员对当天的生产和质量情况进行总结,并定期在车间以予公示;
34. Training on the use of measuring instruments was conducted for all workshop employees. In the structural workshop: Adhere to regular meetings to enhance employees' quality awareness; at the end of each production day, the quality inspector summarizes the day's production and quality conditions, and regularly publishes them in the workshop for public display.
35. 回顾一月以来的活动开展,我们全体KF工作人员严格按照公司及部门指示和要求精心组织、合理安排、用心参与、全面实施、逐步推进并不断完善,圆满完成了此次活动的各项具体资料与要求,取得了可喜的成效,到达了理想的目的。透过认真分析问题的症结,提出合理的
36. 质量月活动期间KF用心开展了岗位大练兵活动,在同事中间组织了“群众标兵”和“个人标兵”工作质量评比活动,使职工的干劲十足,开展你追我赶“争做标兵”的喜人局面,涌现出了优秀的岗位能手,质量与安全管理标兵,他们是我们全体KF工作人员的学习榜样,是我们的楷模,更是我们的追求目标。由标兵为先锋以点带面,让先进的更先进,让后进的赶先进。
35. Looking back on the activities carried out over the past month, all of us at KF have meticulously organized, carefully planned, wholeheartedly participated, fully implemented, gradually advanced, and continuously improved our efforts, successfully completing all the specific materials and requirements of this event. We have achieved encouraging results and reached the desired objectives. By thoroughly analyzing the root causes of the problems, we have proposed reasonable solutions. 36. During the Quality Month activities, KF has wholeheartedly carried out the "Great Training" event for positions, organized the "Mass Vanguard" and "Individual Vanguard" work quality assessment activities among colleagues, which has greatly boosted the enthusiasm of the employees, creating a pleasant atmosphere of competing to be the vanguard. Outstanding position experts, quality and safety management vanguards have emerged, and they are the learning models for all of us at KF, our paragons, and our pursuit goals. By taking the vanguards as the vanguard, we lead the way and encourage the advanced to become even more advanced, and the lagging ones to catch up with the advanced.
37. 、9月7日—9月10日为施工单位自查自改阶段,9月11—9月15日寰球现场项目部组织对施工现场进行第一次施工现场的质量大检查(三查四定或中交前大检查),公布检查结果,整改单位应及时安排对存在的问题进行整改并举一反
37. From September 7th to September 10th is the self-inspection and self-correction stage for the construction unit. From September 11th to September 15th, the Global Field Project Department will organize the first quality inspection of the construction site (either the "Three Inspections and Four Determinations" or the pre-handover large-scale inspection), announce the results of the inspection, and the organizations needing rectification should promptly arrange for the rectification of existing problems and take appropriate measures.
38. 为了提高机械厂产品质量,提高员工的工作质量和积极性,提高部门人员责任心,增强企业凝聚力,xx年9月我厂开展了以“全员行动,提高质量”为主题的“质量月”活动,在公司事业部的领导下,各车间高度重视、精心组织、严格要求,各车间的质量水平取得了显著的成效,产品质量有了大幅度的提升。现将活动有关情况总结如下:
38. In order to improve the quality of products in the machinery factory, enhance the work quality and enthusiasm of employees, increase the sense of responsibility among department personnel, and strengthen corporate cohesion, in September of the XX year, our factory launched a "Quality Month" activity with the theme of "All-for-One Effort, Improve Quality." Under the leadership of the company's business department, each workshop attached great importance to the activity, organized it meticulously, and imposed strict requirements. As a result, the quality levels of each workshop achieved remarkable results, and the quality of products saw a significant improvement. The following is a summary of the relevant activities:
39. 八冶项目部、盛华项目部、华油工建项目部、中核二三项目部要根据质量管理体系文件要求,结合实际情况,认真组织落实本部门质量管理体系文件编制完善工作。各项目部要针对监督站、业主工程部(项目分部、质量组)、监理以及寰球公司现场项目部各类质量检查中发现的问题,举一反三,认真查找本单位、本项目存在的质量问题和不足,结合“质量月”活动,进一步检查所制定的纠正措施或预防措施的落实情况,持续改进,确保质量管理体系运行良好。具体要求如下:
39. The Bayi Project Department, Shenghua Project Department, China National Petroleum Corporation Engineering Construction Project Department, and China National Nuclear Corporation Project Department No. 2 and 3 shall, in accordance with the requirements of the quality management system documents, combine them with the actual situation, and seriously organize and implement the improvement of the quality management system document preparation work in their respective departments. Each project department shall, in response to the issues found in various quality inspections conducted by the supervision stations, the owner's engineering department (project branch, quality group), supervision, and the on-site project department of the Huanqiu Company, learn from one case to avoid similar ones, carefully identify the existing quality problems and deficiencies in their respective units and projects, and, in conjunction with the "Quality Month" activities, further inspect the implementation of the corrective and preventive measures formulated, continuously improve, and ensure the smooth operation of the quality management system. The specific requirements are as follows:
40. 与8月份相比,冲压系统的产品质量明显得到了提高,客户的退货和反馈明显降低,冲压件的各项尺寸基本都能按照客户图纸要求执行。
40. Compared to August, the product quality of the stamping system has been significantly improved, with a noticeable decrease in customer returns and feedback. The dimensions of the stamping parts are generally able to be executed according to the customer's drawings.
41. 德育处做好德育干部专项工作分片管理和交叉工作责任制,邓月海、高丽华七年级,王明强、宋爱军八年级,每天在年级工作时间不少于半天,针对年级出现的问题,随时解决。
41. The Moral Education Department should properly manage the special work of moral education cadre by region and the joint responsibility system of inter-regional work. Deng Yuehai and Gao Lihua for Grade 7, Wang Mingqiang and Song Aijun for Grade 8, should spend no less than half a day working in their respective grade every day, addressing issues as they arise in the grade in a timely manner.
42. 落实《质量发展纲要(2011—2020年)》,以提高项目工程质量为核心,落实质量管理提升工作要求,开展质量指标量化分析,推进质量管理体系建设,开展管理体系融合,提高项目部及各承包商基础管理能力,为业主提供优质工程和服务,确保质量安全,以质量发展打造寰球公司品牌。
42. Implement the "Quality Development Outline (2011-2020)", focusing on improving the quality of project construction, implement the requirements for enhancing quality management, carry out quantitative analysis of quality indicators, promote the construction of quality management systems, carry out the integration of management systems, improve the basic management capabilities of project departments and all contractors, provide high-quality projects and services for owners, ensure quality and safety, and build the brand of China National Petroleum Corporation through quality development.
43. 安排好 6月9日的国旗下,一是学校领导讲,做好全校的宣传发动。二是教师代表讲话,如何提高学生学习成绩。三是学生代表讲话,如何遵规守纪,认真学习,提高成绩。通过国旗下讲话,激励号召全体师学发奋工作、刻苦学习,讲诚信,争做文明学生。
43. Arrangements have been made for the flag-raising ceremony on June 9th. First, school leaders will give a speech to promote and mobilize the whole school. Second, a teacher representative will speak about how to improve students' academic performance. Third, a student representative will speak about how to observe rules and discipline, study diligently, and improve grades. Through the speeches at the flag-raising ceremony, we aim to inspire and mobilize all teachers and students to work hard, study diligently, be honest, and strive to be civilized students.
44. 出车间以后的质量投诉不超12次(市场投诉4次、成品库投诉8次)。
44. The number of quality complaints after leaving the workshop should not exceed 12 (4 market complaints and 8 finished goods warehouse complaints).
45. 为了提高联发公司产品质量,增强员工质量意识,加强管理层人员职责心,公司开展了以“抓质量、强质检、创品牌、塑形象”为 主题 的“质量月”活动,回顾一个月以来的活动开展,各基层单位按照公司指示和要求精心组织、合理安排、用心参与、逐步推进并不断完善,圆满完成了此次活动的各项具体资料与要求,取得了可喜的成效,到达了理想的目的。透过认真分析问题的症结,提出合理的
46. 为了更好开展质量月活动,公司 书记 史秋影主持召开了各基层单位 书记 动员会,会议主要资料是宣传“降本保效保安稳工作”和如何动员全体职工抓质量、如何运用质检手段抓质量、如何体现抓质量成效的工作安排,同时期望各单位做好宣传和落实。
45. In order to improve the quality of products at the United Development Company, enhance the quality awareness of employees, and strengthen the sense of responsibility of management personnel, the company launched a "Quality Month" activity with the theme of "抓质量, 强质检, 创品牌, 塑形象". Reviewing the activities carried out over the past month, all grassroots units organized carefully, arranged rationally, participated wholeheartedly, gradually advanced, and continuously improved, successfully completing all the specific materials and requirements of this activity, achieving satisfying results and reaching the desired goals. By carefully analyzing the root causes of problems, reasonable suggestions were proposed. 46. To better carry out the Quality Month activity, the company secretary Shi Qiuying presided over a mobilization meeting for the secretaries of all grassroots units. The main content of the meeting was to promote the "Reducing Costs, Ensuring Efficiency, Ensuring Safety, and Maintaining Stability" work and to discuss how to mobilize all employees to focus on quality, how to use quality inspection methods to ensure quality, and how to reflect the effectiveness of quality improvement in work arrangements. At the same time, it was expected that all units would do a good job of publicity and implementation.
47. 全体学生在质量月期间定立自己的奋斗目标和行为保证并向老师和家长做出书面承诺;
47. All students will establish their own struggle objectives and behavioral guarantees during the Quality Month and make written commitments to their teachers and parents.
48. 防城港核电项目根据中广核工程公司安全质量国际标杆建设及标杆班组建设要求,结合项目部实际,按照安全质量国际标杆建设要素要求,查漏补缺,对项目部质量管理和班组质量管理中存在的漏洞和不足进行分析,制定改进目标,明确提升方向,通过实体检查和与班组一线员工交流的方式,积极推动项目部质量管理。
48. The Fangchenggang Nuclear Power Project, in accordance with the requirements of China General Nuclear Power Group Engineering Company for the construction of international safety and quality benchmarks and the construction of benchmark teams, and combining with the actual situation of the project department, follows the requirements of the safety and quality international benchmark construction elements, identifies gaps and deficiencies, analyzes the loopholes and shortcomings in the quality management of the project department and team quality management, sets improvement objectives, clarifies the direction of improvement, actively promotes the quality management of the project department through physical inspections and exchanges with frontline employees of the teams.
49. 通过此次活动的开展,各工段的细小环节得到了有效的控制。前段工序中板件的轻拿轻放,机械的勤修勤检,工艺的细致指导,孔位、槽位尺寸的偏差得到了有效的控制;中段工序面油、底油的操作及技能得到了较大的改进提高;后段包装部通过培训,突破重点、难点,抓尾货,少包、错包等现象得到有效的遏制;来料处针对板件的划伤等质量问题提出和制定了切实可行的方案,同时派员驻厂跟踪,大大的降低了由于来料原因而降低生产效力的比率,实现了生产与计划同步的喜人局面。
49. Through the implementation of this activity, the fine links in each section have been effectively controlled. The gentle handling of sheet metal parts in the early stages, regular maintenance and inspection of machinery, and detailed guidance on technology have effectively controlled deviations in hole and slot dimensions; the operation and skills of surface oil and bottom oil in the middle section have been significantly improved; the packaging department in the later stage, through training, has broken through key and difficult points, and phenomena such as the last batch of products, less packaging, and wrong packaging have been effectively contained; the incoming materials section proposed and formulated practical and feasible solutions for quality issues such as scratches on sheet metal parts, while also sending personnel to the factory for tracking, greatly reducing the rate of reduced production efficiency due to incoming materials, and achieving a pleasing situation where production and planning are synchronized.
50. 各单位对“质量月”所取得的实效进行了认真的总结。“质量月”期间,各单位共悬挂横幅和张贴标语139条、发放“质量月”宣传材料911份、制作“质量月”活动展板、专栏、专刊等95期、举办质量教育培训123期次、参加质量教育培训的人数2809人次、参加质量知识竞赛的人数719人次。评选表彰质量先进个人68人次、精品项目和亮点项目32项。一年一度的全国“质量月”活动如期完成并达到了预定效果,但“质量”是个永恒的 主题 。我们将以“质量月”为契机,不断强化和提高广大员工的质量安全意识,激发了大家参与质量安全管理的热情,提升了施工人员进行质量安全控制的实际能力,为实现公司质量安全目标,为公司的发展起到了积极推动作用。
50.各单位对“质量月”所取得的实效进行了认真的总结. During the "Quality Month", a total of 139 banners and slogans were hung, 911 promotional materials for "Quality Month" were distributed, 95 issues of activity boards, columns, and special publications were produced, 123 sessions of quality training and education were held, with 2,809 people participating in the training, and 719 people participating in the quality knowledge competition. 68 individuals were selected and commended for their contributions to quality, and 32 excellent and highlight projects were recognized. The annual national "Quality Month" activity was completed as scheduled and achieved the expected results, but "quality" is an eternal theme. We will take the "Quality Month" as an opportunity to continuously strengthen and improve the quality and safety awareness of all employees, stimulate everyone's enthusiasm for participating in quality and safety management, enhance the practical ability of construction personnel to control quality and safety, and play a positive role in achieving the company's quality and safety goals, and promoting the company's development.
51. xx年“质量月”活动的通知》,制定了“质量月”活动方案,对“质量月”活动作了具体的安排和布置。
51. "Notice of the Quality Month Activity in the Year of XX," formulated the plan for the "Quality Month" activity, and made specific arrangements and preparations for the "Quality Month" activity.
52. 为了确保实现“十一五”期间建筑业施工产值能耗下降20%,每年环比下降44%的目标,确定企业施工产值能耗基数,项目部开展节能降耗统计工作,对正在施工的尾水洞的万元施工产值能耗进行详尽统计,派专人负责进行监督落实,提高能耗统计的上报率和准确率,为贯彻落实建筑业建筑业节能降耗的目标管理打下扎实基础。
52. In order to ensure the achievement of the goal of reducing energy consumption in the construction output value by 20% during the "11th Five-Year Plan" period, with an annual year-on-year decrease of 44%, it is determined to establish the energy consumption base for enterprises' construction output value. The project department carries out energy-saving and consumption reduction statistics work, conducts a detailed statistics of the 10,000 yuan construction output value energy consumption of the tail water tunnel under construction, assigns special personnel to be responsible for supervision and implementation, improves the reporting rate and accuracy of energy consumption statistics, and lays a solid foundation for the implementation of the energy-saving and consumption reduction goal management in the construction industry.